Permit Library › Other GTA municipalities › Town of Aurora › Water, sewers and hydrants (Operational Services)
Hydrant Meter Permit and Fire Flow Test (Aurora)
Hydrant Meter Permit for construction water under Waterworks By-law 6777-26, and a separate Fire Flow Test Application, from Aurora Operational Services [aurora.ca].
You need it when: You will take construction water from a Town of Aurora hydrant, or need a fire flow test for a project in Aurora.
Why is it needed?
- Taking construction water from a hydrant uses the Town's Hydrant Meter Permit, with a deposit for each hydrant [aurora.ca].
- Fire flow tests are requested on a separate online application [aurora.ca].
When should you apply?
- A bulk water fee is charged for construction, by residential unit or by non-residential floor area [aurora.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Hydrant Meter Permit, completed online [aurora.ca]
- Fire Flow Test Application, completed online [aurora.ca]
- Hydrant deposit [aurora.ca]
How do you submit it?
- Apply on the Town's online Hydrant Meter Permit webform, and request a fire flow test on the Fire Flow Test Application webform [aurora.ca].
What are the fees?
2026 fee: hydrant deposit $2,404 each, bulk water during construction $700 per residential or townhouse unit, metered for high-density units, or $450 per 100 m2 non-residential, and $327 for each fire flow test (Fees and Charges By-law 6737-25, Schedule E) [aurora.ca].
Official pages
Track Hydrant Meter Permit and Fire Flow Test (Aurora) free.