Permit Library › Other GTA municipalities › Town of Aurora › Water, sewers and hydrants (Operational Services)

Hydrant Meter Permit and Fire Flow Test (Aurora)

Hydrant Meter Permit for construction water under Waterworks By-law 6777-26, and a separate Fire Flow Test Application, from Aurora Operational Services [aurora.ca].

You need it when: You will take construction water from a Town of Aurora hydrant, or need a fire flow test for a project in Aurora.

Why is it needed?

When should you apply?

How long does review take?

No review time is published for this permit; ask the City when you apply.

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: hydrant deposit $2,404 each, bulk water during construction $700 per residential or townhouse unit, metered for high-density units, or $450 per 100 m2 non-residential, and $327 for each fire flow test (Fees and Charges By-law 6737-25, Schedule E) [aurora.ca].

Official pages

Track Hydrant Meter Permit and Fire Flow Test (Aurora) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.