Permit Library › Other GTA municipalities › Town of Aurora › Planning applications, heritage and Committee of Adjustment
Removal of Holding Symbol (H) (Aurora)
Removal of a holding (H) symbol from Aurora zoning, governed by the Section 20 Holding Provisions of Zoning By-law 6000-17, applied for through Development Planning [aurora.ca].
You need it when: Your Aurora property is zoned with a holding (H) symbol and you need the Town to remove it so your project can proceed.
Why is it needed?
- Section 20 of Zoning By-law 6000-17 sets out Aurora's holding provisions, published as of April 6, 2026 [aurora.ca].
- Schedule H of Fees and Charges By-law 6737-25 lists a fee for removal of a holding symbol [aurora.ca].
When should you apply?
- Check the holding provision that applies to your property in Section 20 before you apply [aurora.ca].
- Contact the Planning Division (planning@aurora.ca, 905-726-4700) before you submit fees to make sure they are correct [aurora.ca].
How long does review take?
No review time is published for this permit; ask the City when you apply.
What documents does a complete application need?
- Application form and fees [aurora.ca]
- Electronic copies of all plans, drawings, reports and studies, plus one hard copy [aurora.ca]
- Unsecured, flattened PDFs (version 7 or later), multi-page sets combined into one PDF, no larger than ARCH E [aurora.ca]
How do you submit it?
- Submit through the CityView Portal (registration required), plus one hard copy of all plans, drawings, reports and studies [aurora.ca].
- Pay by cheque, dropped at the Planning Department on the 3rd floor of Town Hall or mailed to Development Planning Division, 100 John West Way, Box 1000, Aurora ON L4G 6J1 [aurora.ca].
What are the fees?
2026 fee: Schedule H lists base fees of $11,555 and $19,341, including the processing fee, under Removal of Hold (H) Symbol / Temporary Use, without clearly saying which applies to which (Fees and Charges By-law 6737-25) [aurora.ca].
Official pages
- Zoning By-law 6000-17, Section 20 holding provisions (PDF)
- Schedule H, Development Planning fees, 2026 (PDF)
- Development Planning
Track Removal of Holding Symbol (H) (Aurora) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.