Change of Use Permit (Aurora)
Change of use permit from the Aurora Building Division under section 10 of Building By-law 6096-18 and section 10 of the Building Code Act [aurora.ca].
You need it when: You change the use of a building or part of one in Aurora, including an existing two-unit house, which the Town says needs a Change of Use Permit or Building Permit.
Why is it needed?
- Building By-law 6096-18 sets out the change of use permit in s. 10 [aurora.ca].
- Section 10 of the Building Code Act is the provincial basis for a change of use permit, and the Ontario Building Code, O. Reg. 163/24, applies in every Ontario municipality [ON].
- For an existing two-unit house, the Town says a Change of Use Permit or Building Permit is required [aurora.ca].
When should you apply?
- To check first what Zoning By-law 6000-17 requires, the Building Division offers a Preliminary Zoning Review [aurora.ca].
- A two-unit house must meet the Zoning By-law, the Building Code and Registration By-law 6660-24, and is then registered with Building Services [aurora.ca].
- A unit that existed before November 16, 1995 needs a Central York Fire Services fire inspection, and the unit needs an ESA inspection before registration [aurora.ca].
How long does review take?
Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish, the Town's building permit form [aurora.ca]
- Building permit supporting forms the Town lists, such as the Declaration of Use form and the 2024 Building Code Data Matrix [aurora.ca]
- For a two-unit house, the Registration Application for a Second or Third Dwelling Unit [aurora.ca]
How do you submit it?
- Apply through the CityView Portal at cvportal.aurora.ca, by email to building@aurora.ca, or on a USB drive in person [aurora.ca].
- Building Division: building@aurora.ca, (365) 500-2081, Town Hall, 100 John West Way [aurora.ca].
What are the fees?
2026 fee: $8.75 per m2 for a change of use (Fees and Charges By-law 6737-25, Schedule G) [aurora.ca]. A Preliminary Zoning Review is $103 for a single, semi or street townhouse and $203 for all other building types (Schedule B) [aurora.ca]. Fees are payable in full when you apply (Building By-law 6096-18 s. 19.1) [aurora.ca].
Forms and guides
- Aurora Building By-law 6096-18 (office consolidation, as amended) (Town of Aurora, by-law)
- Aurora Building Permit Fee Handout 2026 (Town of Aurora, fee schedule)
- Aurora Application for a Permit to Construct or Demolish (Town of Aurora, application form)
Official pages
Track Change of Use Permit (Aurora) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.