Change of Use Permit (Aurora)

Change of use permit from the Aurora Building Division under section 10 of Building By-law 6096-18 and section 10 of the Building Code Act [aurora.ca].

You need it when: You change the use of a building or part of one in Aurora, including an existing two-unit house, which the Town says needs a Change of Use Permit or Building Permit.

Why is it needed?

When should you apply?

How long does review take?

Plan for about 20 business days. Building Code Div. C 1.3.1.3 [ON]

What documents does a complete application need?

How do you submit it?

What are the fees?

2026 fee: $8.75 per m2 for a change of use (Fees and Charges By-law 6737-25, Schedule G) [aurora.ca]. A Preliminary Zoning Review is $103 for a single, semi or street townhouse and $203 for all other building types (Schedule B) [aurora.ca]. Fees are payable in full when you apply (Building By-law 6096-18 s. 19.1) [aurora.ca].

Forms and guides

Official pages

Track Change of Use Permit (Aurora) free.
Start with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Track this permit free

Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.