Building Permit: Complex Building, High-rise or High-hazard (Aurora)
Building permit under Aurora Building By-law 6096-18 section 6 [aurora.ca]. Complex buildings include high buildings, post-disaster buildings and high-hazard industrial buildings [ON].
You need it when: You build a high building, a post-disaster building or a high-hazard industrial building in Aurora, the complex building class of the Building Code.
Why is it needed?
- The Ontario Building Code, O. Reg. 163/24, applies in every Ontario municipality and treats complex buildings as their own class [ON].
- Work started without a permit draws a Special Investigation Fee of half the permit fee or $309, whichever is greater (2026 Schedule G) [aurora.ca].
When should you apply?
- The Town may accept or refuse an incomplete application, and an accepted one needs the Acknowledgement of Incomplete Application form (Building By-law 6096-18 s. 5.2) [aurora.ca].
- To start the foundation or structure before the full permit issues, ask about a partial permit (s. 7) or a conditional permit (s. 9) under Building By-law 6096-18 [aurora.ca].
- If the work uses the road, boulevard or sidewalk, fill in the Pre-Screening Questionnaire for Road Occupancy and get a Road Occupancy Permit before you begin the work [aurora.ca].
How long does review take?
Plan for about 30 business days. Building Code Div. C 1.3.1.3 [ON]
What documents does a complete application need?
- Application for a Permit to Construct or Demolish [aurora.ca]
- OBC 2024 Data Matrix for Part 3 [aurora.ca]
- Declaration of Use form and Energy Efficiency Design Summary [aurora.ca]
- General Review Letter of Commitment [aurora.ca]
- Plumbing and Drain Permit application for drains, sewers and water services [aurora.ca]
- Files named to the Town's File Naming Requirements for Electronic Submissions [aurora.ca]
How do you submit it?
- Apply on the CityView Portal at cvportal.aurora.ca, by email to building@aurora.ca, or on a USB drive in person [aurora.ca].
- Building Division questions go to building@aurora.ca or (365) 500-2081 [aurora.ca].
What are the fees?
2026 fee: charged per m2 under Schedule G of Fees and Charges By-law 6737-25, with a $687 minimum [aurora.ca].
Forms and guides
- Aurora Building By-law 6096-18 (office consolidation, as amended) (Town of Aurora, by-law)
- Aurora Building Permit Fee Handout 2026 (Town of Aurora, fee schedule)
- Aurora Application for a Permit to Construct or Demolish (Town of Aurora, application form)
Official pages
- Applications, permits and inspections
- Application to construct or demolish
- 2026 building fees (Schedule G)
Track Building Permit: Complex Building, High-rise or High-hazard (Aurora) free.
Track this permit freeStart with a 7-day Team trial with alerts and your whole team, then keep one permit free.
Sources are marked in the text: [TO] toronto.ca pages, [Guide] general industry guidance, [Plan] permit planning practice. Confirm on the official page before applying.