Submission checklists › Urban Forestry

Ravine and Natural Feature Protection (RNFP) Permit

City of Toronto: Parks, Forestry & Recreation (Urban Forestry) · version October 29, 2021, Rev. 2.0 (first issued June 25, 2021)

Cover letter including

1Brief description of the project including:
  • Scope of work
  • Closest municipal address(es)
  • Reason trees and/or vegetation are being impacted (i.e. road widening, station construction, laydown, etc.)
  • Indication if work is also in a Toronto and Region Conservation Authority (TRCA) regulated area, and confirm if a TRCA Voluntary Project Review (VPR) application will be pursued
  • Details on commitment to compensation/restoration
2Figure of the study area showing work area, access, laydown, utility relocation (if applicable), and RNFP and TRCA regulation limits (if applicable)
3Identify tree removal start date, total number of removals and injuries, approximate time for work to be completed (estimate), and reference the Tree Summary Table (see below).
4List of drawings and technical/supporting documentation

Tree Summary Table (refer to template in Attachment 1). Note: the table will be used as an attachment to the final issued permit

5Extract information from the Tree Inventory Table in the Arborist Report to create a summary table of the following: tree identification number/grouping information, diameter at breast height (DBH), species, reason for removal/injury, address, removal/injury, compensation ratio, tree category, identify if heritage or memorial tree
6Sort table by type (removal vs. injury). Do not include dead trees, but provide a separate list of dead trees.

Application form

7Completed and signed RNFP application form

Administrative documentation

8Private property owner's information for private trees proposed for injury or removal, if applicable: name, address, phone number and email; tree identification number in accordance with the Arborist Report
9Confirmation of property ownership, if a change of ownership is anticipated (e.g. transfer of easement, licence agreement, etc.). A copy of the relevant ownership documents and property sketches may be provided.
10Completed City of Toronto Boundary Tree Permit Application

Technical / supporting information

11Legal Plan of Survey or Site Plan, including:
  • Footprint of existing and proposed building(s), underground foundation extensions, building entrances, driveways, paved areas, etc.
  • Existing and proposed grades at the perimeter and within the site itself, including grades for all exterior landscaped areas
  • Property line based on survey information
  • Existing and proposed easements
  • RNFP limit delineated on the plans, as well as the TRCA regulation limit if applicable (RNFP boundary lines should be obtained from the City of Toronto's digital version of OpenData)
  • Limit of construction, access points/routes, property boundary lines, existing landmarks/buildings, addresses
12A sketch/markup of the Site Plan, provided separately, that includes access points/routes, staging/laydown areas and stockpile areas (if any)
13Landscaping and/or Restoration Plan
  • Cross-section details for all proposed hard surface elements within the RNFP area
  • Proposed soft landscaping features, including planting details and plant lists
  • Proposed replacement trees, indicating species and size (DBH)
14Removal Plan:
  • All existing trees, noting trees proposed for removal, injury or preservation, including species and size (DBH) and tree identification number in accordance with the Arborist Report
  • Tree protection (LDH, HDH), Tree Protection Zone (TPZ)
15Grading Plan, if applicable
16Arborist Report, prepared by a qualified arborist or forester in accordance with the City of Toronto's Arborist Report for Development Application:
  • Details and conditions of existing trees: list containing tree number, species, size DBH (cm), condition, tree category, and to remove/injure/protect in accordance with a Tree Preservation Plan, showing appropriate Tree Protection Zones
  • Summary table including: total count by tree category; injury/removal; compensation for each tree category and total compensation
  • Photos: trees to be removed/injured clearly identified; dead trees
  • Identify any trees on lands that are exempt from the City by-law (e.g. provincial or federal lands) and include a statement that those trees are not subject to this permit application. Include a separate list of those tree removals within the inventory table.
  • Details on pruning, if applicable
17Geotechnical Report, if applicable (i.e. if grading is proposed), including:
  • Soil conditions and slope stability
  • Proposed drainage, including construction sediment/drainage control plan
  • Measures taken to protect the stability of the ravine slope

Prior to removal/injury, the following must be provided to Urban Forestry

18Photos of installed tree hoarding (identify tree ID # in photos)
19Completed Owner's Authorization (if the applicant is not the owner)
20Completed Certificate of Insurance (required when the RNFP area is on City-owned land)
21Agreement for Arborists to Perform Arboricultural Services on City Owned Street Trees

Notes

22RNFP trees are protected under the Ravine and Natural Feature Protection By-law (Chapter 658)
23Further guidance on tree planting and plant lists: toronto.ca → Tree planting
24For further guidance, refer to the Guidelines for Completion of an Arborist Report
25Further guidance on Construction Specifications Near Trees
26Permission from the City is required prior to accessing a City-owned or operated property, including parkland, where such permission has not otherwise been granted (e.g. through a land access agreement).
27Fees: no permit fees for RNFP applications
28Compensation:
  • For RNFP trees in a manicured area with a stem-based approach, the replacement ratio is 1:1 for injuries and 3:1 for removals ($583/tree). For a naturalized area, an area-based approach can apply ($26/m²).
  • The proponent/contractor (as applicable) is to meet with the City to discuss and agree upon the permitting and compensation approach (stem-based or area-based) prior to permit application submission.
  • Compensation cash-in-lieu must be provided to Urban Forestry with the application for all trees removed/injured that are not shown to be replaced/planted on the Landscape/Planting/Restoration Plan.
  • If Landscape/Planting/Restoration Plans are updated after permits are issued and cash in lieu has been paid, refunds are provided by the City after review and approval of the plans.

Permits this checklist is for