City of Toronto: Toronto Water · version May 14, 2021, Rev. 1
Application form
| 1 | Fire Hydrant Use Permit Application (online): secure.toronto.ca/webapps/whp/ |
Process following online application
| 2 | Step 1: Book a "Turn On / Turn Off" appointment. Appointments can be made between 8 a.m. and 1 p.m., Monday to Friday. Toronto Water staff will call within four business days of receiving the application to confirm the location of the hydrant(s) and schedule a time on the requested date(s) to turn the hydrant on and off. |
| 3 | Step 2: Hydrant "Turn On" date. Bring a 5 cm (2-inch) fire hose for each hydrant, and a chain and lock. City staff install a water meter to track water use, a gate valve and a backflow valve, then step away so the permit holder (or representative) can install their hose, bib, chain and lock. |
| 4 | Step 3: Hydrant "Turn Off" date. Meet staff at the agreed date and time so they can remove the chain and lock, hose, meter and backflow prevention device. If you fail to arrive, staff will attempt to call you; if you cannot be reached, staff will turn off the hydrant, cut the chain and remove the backflow device and meter. Staff record the amount of water used from the meter, which is used to process any refunds or invoices. |
Applicant responsibility
| 5 | The applicant is responsible for:
|
Notes
| 6 | You can apply, pay for and receive Fire Hydrant Use and/or Fire Hydrant Flow Test permits online between April 15 (pending suitable weather) and November 15. After submitting online you receive a receipt by email, the permit(s) and CSR number(s). |
| 7 | The City grants permits to allow the use of water from fire hydrants between April 15 (pending suitable weather) and November 15. |
| 8 | Permits during the off-season (November 16 to April 14) are granted case by case and applicants must adhere to strict criteria. For an off-season permit contact TWC@toronto.ca for an exemption. |
| 9 | Online application and payment must be made at least 10 business days in advance of the requested date. Once processed, you receive a receipt, the permit(s) and CSR number(s) for future reference. |
| 10 | The CSR number(s) are used by the permit holder (or representative) to pick up the water meter device from Toronto Water. |
| 11 | Fees:
|
This checklist identifies the scope of information typically required to support processing of an application. It is the responsibility of the applicant to consult with the approval authority prior to application submission to confirm the submission requirements for more complex or atypical applications.
Permits this checklist is for
Official pages
Track this submission free.
Track this permit freeDeadlines in business days, email alerts before decisions are due, and your whole team in one place.