Cover letter including

1Brief project description and description of the work
1Contents of the submission

Application forms

2Application For a Permit to Construct or Demolish Form
3Commitment to General Reviews By Architect and Engineers Form – Structural, Shoring, Vibration
4Tree Declaration Form
5Vibration Control Declaration Form, including zone of influence map, pre-construction survey and monitoring program
6Vibration Control and Zone of Influence Report
7Green Roof Declaration Form

Plans and drawings

8Structural Drawings
9Architectural Drawings (as required for information)
10Mechanical Drawings (as required for information)
11Electrical Drawings (as required for information)
12Construction Details and Notes
13Ontario Building Code Supplementary Standard SB-10 Project Information Plan

Technical supporting information

14Building Code Compliance Report
15Structural Calculations
16Geotechnical Engineering Report

Notes

17Fees. Note: upon submitting all the required forms and documents, the City will send a submission status letter, indicating any deficiencies or, if complete, providing the required fees.
18A Part Permit Application must contain the Main Building Permit Folder number.
19A Part Permit can only be submitted once the main Building permit has been submitted and accepted. The Main Building Permit (BLD) must be submitted and, if not fully completed, the Building Division Director will provide approval to proceed with the acceptable percentage of completed documentation.
20This Permit Application Checklist should be read in conjunction with the Permit Application Checklist – General Notes.

Submission requirements for building permit application are governed by Article 3 of Toronto Municipal Code, Chapter 363. This checklist identifies the scope of information typically required to support processing of this type of application in accordance with Chapter 363. Nevertheless, it is the responsibility of the applicant to consult with the approval authority prior to application submission to confirm the submission requirements for more complex applications. This checklist is not intended to be exhaustive. Other information necessary for the complete review of the building permit submission may be required by the Chief Building Official and in accordance with § 363.

Permits this checklist is for

Track this submission free.
Deadlines in business days, email alerts before decisions are due, and your whole team in one place.
Track this permit free